Nigeria’s Federal Government says the 750-kilometre Lagos-Calabar Coastal Highway remains on schedule. Works Minister David Umahi confirmed progress across multiple sections last week. He dismissed suggestions the government had shifted attention to the East-West Road at the coastal highway’s expense.
Section One, covering 147.47 kilometres through Lagos, is under active construction. Section Two spans 55 kilometres. Umahi said its pavement would be complete by mid-November 2026, giving investors a near-term delivery milestone to track.
Key southern sections record over 40% completion
Sections Three A and Three B run through Akwa Ibom and Cross River states. Together they cover approximately 70 kilometres. Umahi said progress on these sections had exceeded 40 per cent. That pace is ahead of the original schedule, according to the minister.
Section Five, also in Akwa Ibom, covers 62.5 kilometres. The minister said it had recorded more than 20 per cent progress in under three months. That rate indicates strong contractor mobilisation across the southern corridor. Construction on Sections Four A and Four B is also continuing.
The highway crosses multiple states and connects coastal commercial centres from Lagos to Calabar. Its scale makes it a direct test of Nigeria’s capacity to deliver large multi-state infrastructure. Progress on several fronts at once strengthens the case that execution risk is being managed.
What does the proposed East-West Road integration mean for investors?
The Works Ministry has sought presidential approval to bring roughly 400 kilometres of the East-West Road into the programme. The proposed corridor runs from Edo through the Niger Delta to Akwa Ibom and Cross River. Survey teams are already working across Edo, Delta, Bayelsa and Rivers states.
Umahi said flood damage had affected parts of the East-West Road in Delta and Edo. He described the proposed work as complementary to the coastal highway, not a replacement. The ministry’s approach would combine new construction with targeted rehabilitation along flood-affected stretches.
For investors, the two models carry different funding and maintenance profiles. New-build sections require heavier upfront capital. Rehabilitation work can move faster but demands sustained maintenance budgets. The distinction shapes project-finance structures and long-term returns.
Umahi confirmed the coastal highway’s alignment will not change. He called it a federal legacy infrastructure project. ‘The coastal highway’s progress now depends on execution across several connected corridors,’ a position consistent with the ministry’s multi-section rollout strategy.
Investors should watch the mid-November 2026 deadline for Section Two and track any presidential decision on the 400-kilometre East-West Road proposal — those two signals will confirm whether this programme can convert construction activity into a reliable regional transport network.
Quick answers
The Lagos-Calabar Coastal Highway spans 750 kilometres and runs through multiple southern Nigerian states from Lagos to Calabar.
The Works Ministry has set a mid-November 2026 target for pavement completion on Section Two, which covers 55 kilometres.
The Works Ministry has sought presidential approval to include approximately 400 kilometres of the East-West Road — running from Edo through the Niger Delta to Akwa Ibom and Cross River — within the coastal highway programme.