President Daniel Chapo officially opened the project at a ceremony in Maputo. The Maputo Port Development Company (MPDC), the port’s concession holder, is leading the works. CRBC is carrying out the physical dredging operations.
Maputo Port Channel Dredging Project
| Operator | Maputo Port Development Company (MPDC) |
|---|---|
| Contractor | CRBC |
| Material to remove | Approximately 21.2 million cubic metres |
| Max vessel size | Up to 366 metres / 14,000 TEU container ships |
| Duration | Around 12 months |
| Regional link | Mozambique, South Africa, Eswatini and international markets |
Source: October 2026 project announcement, Freight News October 2026
The investment targets marine access and shipping efficiency. It also widens options for cargo moving between Mozambique, South Africa, Eswatini and international markets.
A wider, deeper channel for regional cargo
The project will deepen the channel from 14.4 metres to 15.3 metres, according to October 2026 project details. Straight sections will widen from 110 metres to 210 metres. Bends will expand from 150 metres to 295 metres, giving larger vessels more room to manoeuvre.
Once complete, the channel will accommodate vessels up to 366 metres in length. That includes container ships of up to 14,000 TEU, subject to draft and operating conditions. The works are expected to take around 12 months.
Approximately 21.2 million cubic metres of material will be removed during the project, per the October 2026 project announcement. Port operations will continue throughout, Freight News reported in October 2026. That continuity limits disruption to existing cargo flows.
| Channel dimension | Before | After |
|---|---|---|
| Depth | 14.4 m | 15.3 m |
| Straight-section width | 110 m | 210 m |
| Bend width | 150 m | 295 m |
| Maximum vessel length | Not disclosed | ~366 m |
What does this mean for southern African trade investors?
Maputo’s geography gives the upgrade commercial weight beyond Mozambique’s borders. The port links industrial and mining markets across southern Africa. It handles cargo tied to South Africa and Eswatini. Larger vessels improve scale economics for exporters and shipping lines using the corridor.
By FurtherAfrica’s reading of the numbers, deeper access converts port capacity into a broader regional trade option. The dredging forms part of a wider expansion at Maputo Port. A longer concession horizon supports further capital spending and gives logistics operators time to build volume around improved marine access.
The project connects to Mozambique’s wider logistics ambitions. The coastal cabotage programme links five major ports along the country’s coastline. The Mozambique-Botswana rail corridor targets a US$6.5B inland link. Together, these moves signal a coordinated push to position Mozambique as a primary gateway for landlocked southern African markets.
Investors and shipping lines should track construction milestones, vessel call data and cargo volumes through 2027 as the clearest indicators of the project’s commercial return.
Quick answers
The Maputo Port dredging project carries a budget of approximately US$150 million and was officially launched on 12 October 2026 by President Daniel Chapo.
The channel will deepen from 14.4 metres to 15.3 metres, allowing vessels up to 366 metres long and 14,000 TEU capacity to call at the port.
The works are expected to take approximately 12 months and will proceed while the port remains fully operational.