TotalEnergies leads the project alongside Sonangol and Petronas in Block 20/11. The partners are now checking critical equipment before shipments to Angola begin in 2027. The milestone also opens a new phase for subsea contractors and Angolan service providers.
Kaminho Deepwater Project at a Glance
| Operator | TotalEnergies, alongside Sonangol and Petronas |
|---|---|
| Block | Block 20/11, Kwanza Basin, Angola |
| Estimated investment | US$6bn |
| Subsea Christmas trees | 13 units |
| Water depth | More than 1,500 metres |
| Target first production | 2028 |
Source: 2026 project reporting
Johor inspection tests delivery readiness
ANPG Administrator Ana Miala led a delegation to OneSubsea‘s facilities in Johor, Malaysia. Representatives from TotalEnergies, Petronas and Sonangol joined the inspection. The visit focused on the subsea production system for Block 20/11.
Officials reviewed safety standards, quality controls and delivery schedules during the manufacturing checks. The equipment includes 13 subsea Christmas trees. These units will control fluid flows from the wells beneath the South Atlantic.
Shipments to Angola are scheduled to start in 2027. The timetable gives contractors a defined pipeline of logistics, installation and testing work. Once delivered, the equipment will undergo further checks at Sonils in Luanda. Local technical teams will support electromechanical testing before offshore installation.
By FurtherAfrica’s reading of the numbers, Kaminho is moving from fabrication towards integrated field execution. This trajectory supports the broader momentum documented in Angola’s upstream ownership financing drive, where national financing targets of US$5.18B signal sustained commitment to deepwater development.
What does the project mean for investors?
The subsea system will operate below 1,500 metres. It will connect Cameia wells to flow lines leading to the FPSO Kaminho. The floating vessel will separate crude oil, gas and water before export.
This design places specialised subsea engineering at the centre of project delivery. First production is scheduled for 2028. The timing gives investors a clear milestone for tracking construction, installation and commissioning progress.
The project is the first major deepwater oil development in the Kwanza Basin. It therefore provides an operating reference for future frontier-basin investment. Angola also gains a route to expand production from newer resources. Meanwhile, local testing at Sonils can deepen technical capacity around complex offshore systems.
A recent Chevron discovery in Angola hitting a 600-metre oil column adds further weight to the country’s deepwater credentials. Together, these advances position Angola’s Atlantic margin as one of Africa’s most active upstream frontiers.
Kaminho’s halfway milestone turns Angola’s upstream strategy into a measurable delivery story. The main risks now sit in execution, equipment transport and subsea installation. However, the Johor inspection and the 2027 shipment plan provide visible checkpoints for market participants.
According to October 2026 project reporting, all five key indicators are on track. The table below summarises them.
| Project indicator | Verified position |
|---|---|
| Completion | More than 50%, according to October 2026 project reporting |
| Estimated investment | US$6bn, according to 2026 project reporting |
| Subsea Christmas trees | 13 units, according to 2026 project reporting |
| Water depth | More than 1,500 metres, according to project reporting |
| Target start-up | 2028, according to 2026 project reporting |
Investors should watch the arrival of the subsea equipment, Luanda testing results and installation progress as the clearest signals of whether first oil in 2028 remains on schedule.
Quick answers
Kaminho is a US$6bn deepwater oil project in Angola’s Block 20/11, led by TotalEnergies with Sonangol and Petronas as partners.
The project passed 50% completion in October 2026. Its subsea system includes 13 Christmas trees, with equipment shipments to Angola planned from 2027.
Production is scheduled for 2028. The subsea system will connect Cameia wells to the FPSO Kaminho at depths exceeding 1,500 metres.