President João Lourenço signed a presidential decree on 4 November 2026 authorising €201.2 million for the first phase of Angola’s Electricity Grid Expansion Project. The funding covers Lot A, which spans Porto Seco, Funda, Polo Industrial de Viana, Zona Verde and Mundial. More than 500,000 residents stand to benefit.
Angola Electricity Grid Expansion – Lot A
| Decreto | Assinado em 4 de novembro de 2026 por João Lourenço |
|---|---|
| Orçamento autorizado | €201,2 milhões |
| Zonas abrangidas | Porto Seco, Funda, Polo Industrial de Viana, Zona Verde e Mundial |
| Novas subestações | Três, cada uma com 80 MVA |
| Infraestrutura total | 103 quilómetros de linhas de alta e média tensão |
| Beneficiários | Mais de 500.000 residentes |
Source: Decreto presidencial, novembro de 2026
The decree channels public capital into Angola’s largest urban and industrial corridor. It also defines a clear package of transmission and distribution works for suppliers and contractors.
Capacity rises across Luanda’s growth corridor
Three new substations, each rated at 80 megavolt-amperes, form the backbone of Lot A. The project adds a 40 MVA transformer at the Polo Industrial de Viana substation. Together, these works deliver roughly 280 MVA of additional nominal transformation capacity, according to government figures for the first phase.
The infrastructure component covers 103 kilometres in total. That breaks down into 55 kilometres of 60 kilovolt high-voltage overhead lines and 48 kilometres of 30 kV medium-voltage overhead lines. The combined scope addresses upstream grid constraints and local distribution bottlenecks simultaneously.
By FurtherAfrica’s reading of the numbers, the programme allocates approximately €1,610 per targeted home, using the €201.2 million authorisation against 125,000 homes.
| Project measure | Government figure (Nov 2026 decree) |
|---|---|
| Targeted homes | More than 125,000 |
| Beneficiaries | More than 500,000 residents |
| New substations | Three, at 80 MVA each |
| Total new infrastructure | 103 kilometres |
| Total authorised budget | €201.2 million |
What does the deal mean for investors?
Contract execution will follow a simplified procurement procedure. The government justified this route on the basis of external financing. The investment will sit within the Public Investment Programme of the General State Budget.
Minister of Energy and Water João Baptista Borges will oversee implementation. That link between project delivery and a named authority reduces ambiguity for prospective suppliers. The structure offers a sizeable, well-defined work package covering substation equipment, transmission lines and medium-voltage upgrades.
Angola’s grid strategy is drawing wider international interest. In October 2026, ENDE-EP signed a works contract with PROEF Portugal for rural-electrification projects in the Maize Triangle, covering municipalities in Huíla and Cuanza Sul. That separate contract signals a broader pipeline for grid-related contractors across Angola.
The Luanda project carries a distinct commercial profile. It concentrates on dense urban and industrial locations where demand density supports stronger revenue visibility. Angola’s first-quarter 2026 GDP growth reached 5.3%, with public debt at 51.2% of GDP, according to government data — a fiscal backdrop that supports continued public-investment commitments.
Grid capacity is the immediate investment signal the decree sends. Investors should watch the procurement notice, financing terms and award timetable as the next concrete milestones for Lot A.
Quick answers
Angola authorised €201.2 million for the first phase of the Electricity Grid Expansion Project in Luanda and Icolo e Bengo, via a presidential decree signed on 4 November 2026.
Lot A targets more than 125,000 homes and is expected to benefit over 500,000 residents across Luanda and Icolo e Bengo.
The project will add approximately 280 MVA of transformation capacity through three new 80 MVA substations, one additional 40 MVA transformer, and 103 kilometres of new overhead lines split between 60 kV and 30 kV voltages.